We will be having a planned maintenance due to take place on our secondary power feed.
Details of the planned maintenance are as follows :
----------
Start: 21/01/25 @ 9:00 GMT
Latest Finish: 21/01/25 @ 16:00 GMT
Details: Electrical engineers will be performing routine servicing on the substations serving our Data Centre.
During this period, ALL building power, will be transferred from mains to generators. Once the load is being supported solely by generators, the mains will be temporarily disconnected to allow the substations to be serviced. Power will be provided to the UPS via the generators for the duration of the at risk window. During the at risk period both site power feeds will continue to be protected by their respective UPS system and both generators will remain available.
Impact: Works should be transparent to all customers, but should be considered at risk due to mains not being available throughout the works period
----------
Saturday, December 14, 2024